How to score and select new product ideas

How to score and select new product ideas

Updated October 2026.

Most new product ideas should never become projects. The difficulty is to tell which ones, early, before R&D time and trial budgets are spent. A simple, shared scorecard does most of the work.

1. Collect every idea in one place

Ideas come from everywhere: customer and retailer requests, sales, R&D, trends, complaints, cost reduction. Record each one with its origin, its type (new product, renovation, line extension, private label) and a sponsor. An idea without an owner is not reviewed.

2. Screen with a few must-have criteria

Before scoring, remove the ideas that fail a mandatory condition. Answer by yes or no:

  • Does it fit the strategy and the brands?
  • Is it allowed in the target markets (ingredients, claims, labeling)?
  • Can the plants produce it, or with which investment?
  • Is there a customer, a channel or a retailer for it?

3. Score the remaining ideas with weighted criteria

Keep five to seven criteria, scored from 1 to 5, with weights agreed once by Marketing, R&D, Quality and Finance. An example for food and cosmetics:

CriterionWeightQuestion
Market attractiveness25 %Size, growth and price level of the segment
Strategic fit20 %Brand, channel, existing ranges
Technical feasibility15 %Formulation, process, shelf life or stability
Margin15 %Target cost against expected selling price
Regulatory risk15 %Ingredients, claims and labeling in each market
Time to market10 %Can it launch in the targeted window?

The score ranks the ideas; it does not decide alone. Write down the reason for each decision, so that the team can come back to it.

beCPG PLM dashboard: project scores per criterion and per project
Scores per criterion, raw and weighted, and per project (beCPG dashboard).

4. Balance the portfolio

A list of the best scores can still be a bad portfolio: only renovations, or only risky innovations, or too many projects for the same team. Look at the selection as a whole: mix of project types, risk, workload per team and launch dates.

5. Decide at each gate: go, kill, hold or rework

A score is not final. Update it at each gate with what the project has learned: first trials, real cost, customer feedback. Stopping a project at the feasibility gate costs far less than after the industrial trials.

Mistakes to avoid

  • Scoring without weights agreed beforehand: each meeting re-opens the debate.
  • Too many criteria: the score no longer separates the ideas.
  • Never killing a project: the pipeline fills up and every launch slips.
  • Discovering the regulatory risk at the end: check ingredients and claims at the screening stage.

In beCPG

Project templates include an evaluation grid with questions, answers and scores, completed at each stage. The project overview shows the scores of every project side by side, and dashboards analyze the portfolio by family, customer or stage. Discover project management in beCPG PLM.

See also

Read also

Cosmetics & HPC

Improving teamwork with collaborative sites

Product development involves multiple departments: R&D, quality, purchasing, production, marketing, and more. Each team needs easy access to information and must be able to track changes. To meet these needs,…

Pamela Abboud4 min

Cosmetics & HPC

How to choose a PLM software for cosmetics: 10 criteria

To choose a cosmetic PLM software, check ten points: the INCI list, fragrance allergens, regulatory checks per market, toxicology, the PIF, claims, supplier data, packaging, projects and deployment. Ask to see each of them on your own formulas during the demo. If you also make dietary supplements or personal care products, check that a single repository covers them.

Pamela Abboud6 min

See beCPG in action

Request a demo or start your free trial.